+917292009966 +917292006699 Whatsapp
Tasha Realty
 
 

News: HC asks panel to verify how many affordable flats built by Hiranandani Group-04-03-2021

https://realty.economictimes.indiatimes.com/news/regulatory/hc-asks-panel-to-verify-how-many-affordable-flats-built-by-hiranandani-group/81323298

Hiranandani had filed an application to extend timelines given to it in October 2017 to complete construction of four wings of Castle Rock, five wings of Regent Hill, three wings of Atlantis and two buildings —Sorrento and Maple.

MUMBAI: Bombay high court on Wednesday directed a committee to find out how many flats were constructed by Hiranandani group in the Powai Area Development Scheme after its 2017 order allowing it time to complete the constructions.

The order by a bench of chief justice Dipankar Datta and justice Girish Kulkarni was passed on Hiranandani’s application to extend timelines given to it in October 2017 to complete construction of four wings of Castle Rock, five wings of Regent Hill, three wings of Atlantis and two buildings —Sorrento and Maple.

In February 2012, on a PIL, the high court had directed Hiranandani to construct 1,511 flats of 40 sq mts (430 sq ft) and 1,593 flats of 80 sq mts (861) sq ft before undertaking any other construction.

The PIL by activists Kamlakar Satve, Rajendra Thacker and Medha Patkar said Hiranandani had signed a lease for 230 acres of land in 1986 in a tripartite agreement with the state and MMRDA to build affordable housing. The petitioners, however, alleged that the flats were merged into sprawling 4,000-5,000 sq ft apartments and sold at premium rates.

On the developer’s application, the HC in October 2017 had granted time till June 2021 to complete the construction. It had also set up a committee to verify the developer’s claim. The builder has sought that the delay be condoned and further extension of timelines ranging from January 2022 till June 2023 be granted. It cited Covid-19 for the delay.

Senior advocate Milind Sathe for Hiranandani said majority of the flats were ready, but the balance could not be constructed due to the pandemic. He said in October 2017, 887 flats of 80 sq mt were left to be constructed. Of these, 844 flats were constructed and 43 were remaining. Out of 1,511 flats of 40 sq mt, 403 were constructed. But the petitioners’ advocates —Gayatri Singh, Sumedha Rao and Mihir Desai —disputed the figures. They alleged that commercial constructions had been made in breach of the 2012 order and even after October 2017, flats were amalgamated and sold for which BMC had issued notices in 2020.

The judges then reconstituted the earlier committee and directed it to visit the site and submit a report after two weeks. “Find out if all the figures are correct,” said the chief justice.

DISCLAIMER: This website and the Information contained is in the process of being updated and the contents are under review/revision in terms of the Real Estate Regulation Act, 2016 and Rules there under (RERA), and will be reviewed from time to time. Till the time that the contents are fully updated, the same shall neither be construed to be any kind of advertisement, solicitation, marketing, Booking, offer for sale, invitation to offer within the purview of RERA and shall have no binding effect on the Company and nor constitute any offer and/or acceptance and/or contract and/or agreement and/or transaction and/or any intention thereof and/or a disclosure under any statute of any nature whatsoever. Please call to check the updated pricing, status etc. The photographs contained herein may be actual/stock/standard photography or rendered images used for the purpose and have been taken at a location other than the project site and are used to indicate a conceptual lifestyle. Actual product may vary/differ from what is indicated herein. The location info shown are indicative and selective representation of certain elements present/that may be present in and around the city/project site. No representations are made regarding existence/continuity of existence of any landmarks/locations shown. The landmarks/locations may be subject to change from time to time and such changes are completely outside our control. No representation or warranty is made or intended as to the accuracy or completeness of information under this website or as to its suitability or adequacy for any purpose. Before making a decision to purchase, you are requested to independently, either directly or through your legal/financial consultants, thoroughly verify all details/documents pertaining to the respective project as available on the respective RERA sites.The Company is not liable for any consequence of any action taken by the viewer relying only on such material/ information that is presently displayed on this website.