News: Rapid Metro: Haryana told to deposit Rs 1,900 crore for now-28-03-2021

https://timesofindia.indiatimes.com/city/gurgaon/hsvp-asked-to-put-rs-1925-crore-in-escrow-account-in-rapid-metro-row/articleshow/81728520.cms

Rapid Metro: Haryana told to deposit Rs 1,900 crore for now

GURUGRAM: The Haryana government has been directed by the Supreme Court to deposit Rs 1,925 crore within three months into an escrow account while hearing a dispute between the state’s urban development authority, HSVP, and infrastructure company IL&FS on the Rapid Metro corridor in Gurugram.

IL&FS had in September 2019 terminated the Rapid Metro concession agreement, alleging there were multiple obligations that HSVP had not met and demanded payments due to them under the concession agreement. The Supreme Court has asked HSVP to deposit 80% of the total “debt due” (Rs 2,407 crore).

HSVP said it is planning to seek legal opinion and might file a review petition. “I am yet to go through the entire order, but as of now, we will be seeking a legal opinion on this matter,” Ajit Balaji Joshi, HSVP chief administrator, told TOI on Saturday. Joshi is also managing director of Haryana Mass Rapid Transport Corporation (HMRTC).

IL&FS had bagged the Rapid Metro project, which was developed through its subsidiary SPVs – Rapid Metro Rail Gurugram Limited (RMGL) and Rapid Metro Rail Gurugram South Limited (RMGSL) – in 2009 and 2013, in two phases. According to the concession agreement, the asset was to be handed over to HSVP in case of a termination of the agreement and IL&FS was entitled to termination payment of 80% the debt due in case IL&FS defaults and 100% of the debt due in case HSVP defaults.

HSVP challenged this in the Punjab and Haryana high court in September 2019. The high court, after hearing both parties, directed IL&FS to hand over operations and maintenance of Rapid Metro to HSVP. It also asked the Comptroller & Auditor General to carry out a financial audit to determine total debt due and directed HSVP to pay 80% of debt due as determined by CAG.


Acting on the HC order, IL&FS handed over Rapid Metro to HSVP in October 2019 and CAG submitted the debt due report to the HC in September 2020, in which it stated that the total debt due was Rs 2,407 crore. In January 2021, IL&FS moved the Supreme Court, claiming HSVP had failed to comply with the high court order, citing several reasons.


Welcoming the SC decision, an IL&FS spokesperson said, “The order will go a long way in protecting the interest of investors by enforcing legitimate contracts in the infrastructure sector.”


Talking to TOI, Nadim Akhtar advisor planning, HMRTC said he was yet to see the order. “I am suffering from Covid due to which I am yet to go through the order,” he said.


The order was passed on Friday by a three-judge bench of justices DY Chandrachud, MR Shah and Sanjiv Khanna.

DISCLAIMER: This website and the Information contained is in the process of being updated and the contents are under review/revision in terms of the Real Estate Regulation Act, 2016 and Rules there under (RERA), and will be reviewed from time to time. Till the time that the contents are fully updated, the same shall neither be construed to be any kind of advertisement, solicitation, marketing, Booking, offer for sale, invitation to offer within the purview of RERA and shall have no binding effect on the Company and nor constitute any offer and/or acceptance and/or contract and/or agreement and/or transaction and/or any intention thereof and/or a disclosure under any statute of any nature whatsoever. Please call to check the updated pricing, status etc. The photographs contained herein may be actual/stock/standard photography or rendered images used for the purpose and have been taken at a location other than the project site and are used to indicate a conceptual lifestyle. Actual product may vary/differ from what is indicated herein. The location info shown are indicative and selective representation of certain elements present/that may be present in and around the city/project site. No representations are made regarding existence/continuity of existence of any landmarks/locations shown. The landmarks/locations may be subject to change from time to time and such changes are completely outside our control. No representation or warranty is made or intended as to the accuracy or completeness of information under this website or as to its suitability or adequacy for any purpose. Before making a decision to purchase, you are requested to independently, either directly or through your legal/financial consultants, thoroughly verify all details/documents pertaining to the respective project as available on the respective RERA sites.The Company is not liable for any consequence of any action taken by the viewer relying only on such material/ information that is presently displayed on this website.