News: Submit Plan To Fix Basic Infra In Harmony, DTCP Tells Unitech-01.11.2017

Submit plan to fix basic infra in Harmony, DTCP tells Unitech

More than 200 families living in Unitech’s Harmony, a residential society in Sector 50, without occupation certificate and facing several maintenance-related problems, are now looking forward to resolution of their issues. Their problems range from inadequate firefighting equipment to bad roads in the society.

Following a series of complaints from residents, the department of town and country planning (DTCP) has stepped in and directed Unitech to submit a comprehensive plan to resolve the problems. The developer has also been asked to submit details of funds required for completing the basic infrastructure work.

Harmony was launched by Unitech in 2006 and it was expected to be completed by 2009. Spread over 10.50 acres with eight towers, Harmony was delayed like many other real estate projects of the city. The developer delivered the first tower in 2011 and few more towers were delivered in 2014, while the remaining towers were completed in 2016. But till now, the developer has not been able to complete the basic infrastructure work.

“Incomplete infrastructure work coupled with poor maintenance have made our lives difficult. Lifts are in poor condition and firefighting equipment are inadequate and non-functional. Residents are concerned about their safety and security,” said Geetha, one of the residents. “The developer does not pay for housekeeping and security guards, and they keep going on strike.”

Residents alleged the sewage treatment plant and the water treatment plant are non-functional and roads inside the society are in poor condition. “Power infrastructure is also not fully developed due to which society faces regular disruption in supply,” said Geetha.

Some residents claimed that they approached the developer with their complaints many a time, but no action has been taken yet. “One department of the real estate company puts the blame on the other department,” said a resident, who did not wish to be named.

When contacted, district town planner (DTP) RS Batth said, “Unitech has been asked to submit a detailed drawing of the project and estimate for completing the infrastructure deficiencies in Harmony. It has also been directed to take necessary measures to improve fire safety arrangements.”

Unitech admitted there are some infrastructure issues in the society. “We are working to prepare an estimate for infrastructure work. A detailed report with reply to issues raised by department will be submitted (to DTCP) in the next few days,” a spokesperson said.

DISCLAIMER: This website and the Information contained is in the process of being updated and the contents are under review/revision in terms of the Real Estate Regulation Act, 2016 and Rules there under (RERA), and will be reviewed from time to time. Till the time that the contents are fully updated, the same shall neither be construed to be any kind of advertisement, solicitation, marketing, Booking, offer for sale, invitation to offer within the purview of RERA and shall have no binding effect on the Company and nor constitute any offer and/or acceptance and/or contract and/or agreement and/or transaction and/or any intention thereof and/or a disclosure under any statute of any nature whatsoever. Please call to check the updated pricing, status etc. The photographs contained herein may be actual/stock/standard photography or rendered images used for the purpose and have been taken at a location other than the project site and are used to indicate a conceptual lifestyle. Actual product may vary/differ from what is indicated herein. The location info shown are indicative and selective representation of certain elements present/that may be present in and around the city/project site. No representations are made regarding existence/continuity of existence of any landmarks/locations shown. The landmarks/locations may be subject to change from time to time and such changes are completely outside our control. No representation or warranty is made or intended as to the accuracy or completeness of information under this website or as to its suitability or adequacy for any purpose. Before making a decision to purchase, you are requested to independently, either directly or through your legal/financial consultants, thoroughly verify all details/documents pertaining to the respective project as available on the respective RERA sites.The Company is not liable for any consequence of any action taken by the viewer relying only on such material/ information that is presently displayed on this website.