News: Builder liable to pay damages for occupation certificate delay: SC-12-01-2022

https://realty.economictimes.indiatimes.com/news/regulatory/builder-liable-to-pay-damages-for-occupation-certificate-delay-sc/88845987

The SC passed the order on a plea of Mumbai-based Samruddhi Co-operative Housing Society Ltd. Advocate Sunil Fernandes said homebuyers were living in the society for 25 years without occupation certificate and had to pay 25% higher property taxes and 50% higher water charges.

NEW DELHI: In a relief to homebuyers who are forced to take possession of their flats and start living due to delay on part of the builder to get all clearances from the authorities, the Supreme Court on Tuesday held that it would amount to deficiency in services on the part of real estate company if it failed to get occupation certificate and homebuyers could seek compensation.

A bench of Justices D Y Chandrachud and A S Bopanna said builders would be liable to refund the money if the homebuyers were forced to pay higher taxes and water charges arising from the lack of an occupancy certificate.

It set aside the order of the National Consumer Disputes Redressal Commission which had turned down homebuyers’ plea against a builder and held they should approach against the authorities which are charging higher taxes

The SC passed the order on a plea of Mumbai-based Samruddhi Co-operative Housing Society Ltd. Advocate Sunil Fernandes said homebuyers were living in the society for 25 years without occupation certificate and had to pay 25% higher property taxes and 50% higher water charges.

The builder said the plea was barred by limitation as the cause of action arose in 1997 when they took possession but the complaint was filed 18 years later.

DISCLAIMER: This website and the Information contained is in the process of being updated and the contents are under review/revision in terms of the Real Estate Regulation Act, 2016 and Rules there under (RERA), and will be reviewed from time to time. Till the time that the contents are fully updated, the same shall neither be construed to be any kind of advertisement, solicitation, marketing, Booking, offer for sale, invitation to offer within the purview of RERA and shall have no binding effect on the Company and nor constitute any offer and/or acceptance and/or contract and/or agreement and/or transaction and/or any intention thereof and/or a disclosure under any statute of any nature whatsoever. Please call to check the updated pricing, status etc. The photographs contained herein may be actual/stock/standard photography or rendered images used for the purpose and have been taken at a location other than the project site and are used to indicate a conceptual lifestyle. Actual product may vary/differ from what is indicated herein. The location info shown are indicative and selective representation of certain elements present/that may be present in and around the city/project site. No representations are made regarding existence/continuity of existence of any landmarks/locations shown. The landmarks/locations may be subject to change from time to time and such changes are completely outside our control. No representation or warranty is made or intended as to the accuracy or completeness of information under this website or as to its suitability or adequacy for any purpose. Before making a decision to purchase, you are requested to independently, either directly or through your legal/financial consultants, thoroughly verify all details/documents pertaining to the respective project as available on the respective RERA sites.The Company is not liable for any consequence of any action taken by the viewer relying only on such material/ information that is presently displayed on this website.