News: Homebuyers can seek refund if flat delayed beyond 1 year: NCDRC-17-04-2019

https://timesofindia.indiatimes.com/business/india-business/homebuyers-entitled-to-refund-if-possession-is-delayed-beyond-one-year-ncdrc/articleshow/69358262.cms

Updated On: May 17, 2019

NEW DELHI: In a relief to lakhs of aggrieved homebuyers who re forced to wait for possession of their flats for years, the apex consumer commission has quantified a time period of one year for delayed projects beyond which investors can claim refund from builders.

Judicial forums, including Supreme Court and consumer courts, have repeatedly held that homebuyers cannot be made to wait indefinitely, but it was not clarified when refund can beclaimed in case of delay.

Now, the National Consumer Disputes Redressal Commission has held that buyers can seek refund if possession is delayed by one year beyond the date promised by the builder. “It is now established that allottees have the right to ask  for refund if possession is inordinately delayed, particular beyond one year,” a bench of Prem Narain said.

he court passed the order on a plea by Delhi resident Shalab Nigam, who in 2012, bought a flat in the luxury housing project, Greenopolis, in Gurgaon being developed by Orris Infrastructure and 3C company.

Homebuyers info

Nigam had made a payment of around Rs 90 lakh against the total cost of around Rs 1 crore. As per the agreement, the flat was to be handed over within 36 months, with a grace period of six months, from the date of allotment. When the builders failed to complete the project, Nigam approached the commission through advocate Aditya Parolia, seeking its direction for either refund or time-bound possession of the flat.
 

As the buyer preferred to take possession of the flat, the commission directed the builder to complete the construction and hand over the flat, complete in all respects as per the agreement, by end of September 2019 after obtaining occupancy certificate.

The commission directed the builder to pay compensation at the rate of 6% per year on the total deposit for the delayed period even after handing over possession. In case of non-delivery of flat within the deadline prescribed by commission, NCDRC said the builder will have to refund the entire amount with 10% interest.

The builder had contended that the buyer had discontinued paying instalments and if refund is ordered, then there will be a forfeit of 10% of the amount as earnest money, as per the agreed clause. But the commission rejected the contention, saying instalments were paid up to the 7th stage and the payment was stopped later as there was no progress in the construction.

Though in cases of delayed projects, builders often pay compensation as per the clause in agreement which ranges from Rs 5-10 per sq feet per month, the sum is meagre in view of the large investments by buyers.

DISCLAIMER: This website and the Information contained is in the process of being updated and the contents are under review/revision in terms of the Real Estate Regulation Act, 2016 and Rules there under (RERA), and will be reviewed from time to time. Till the time that the contents are fully updated, the same shall neither be construed to be any kind of advertisement, solicitation, marketing, Booking, offer for sale, invitation to offer within the purview of RERA and shall have no binding effect on the Company and nor constitute any offer and/or acceptance and/or contract and/or agreement and/or transaction and/or any intention thereof and/or a disclosure under any statute of any nature whatsoever. Please call to check the updated pricing, status etc. The photographs contained herein may be actual/stock/standard photography or rendered images used for the purpose and have been taken at a location other than the project site and are used to indicate a conceptual lifestyle. Actual product may vary/differ from what is indicated herein. The location info shown are indicative and selective representation of certain elements present/that may be present in and around the city/project site. No representations are made regarding existence/continuity of existence of any landmarks/locations shown. The landmarks/locations may be subject to change from time to time and such changes are completely outside our control. No representation or warranty is made or intended as to the accuracy or completeness of information under this website or as to its suitability or adequacy for any purpose. Before making a decision to purchase, you are requested to independently, either directly or through your legal/financial consultants, thoroughly verify all details/documents pertaining to the respective project as available on the respective RERA sites.The Company is not liable for any consequence of any action taken by the viewer relying only on such material/ information that is presently displayed on this website.