News: Homebuyer can approach both consumer panel and Rera: Delhi HC-10-09-2019

https://timesofindia.indiatimes.com/city/delhi/homebuyer-can-approach-both-consumer-panel-and-rera-hc/articleshow/71056244.cms

 Updated On: Sep 10, 2019

NEW DELHI: In a crucial ruling Delhi high court has held that homebuyers can approach both the National Consumer Disputes Redressal Commission (NCDRC) and Rera against errant builders as their jurisdictions are “concurrent”.

The court said proceedings under the Consumer Protection Act, 1986 can be started by homebuyers (or allottees of properties in proposed real estate development projects) against developers even after enactment of the Real Estate (Development and Regulation) Act, 2016 commonly known as Rera.
Justice Prateek Jalan, in the process, dismissed a batch of petitions filed by 62 builders and developers across the national capital region who had sought relief, arguing that once a homebuyer moved RERA, the case pending earlier against them before the consumer commission couldn’t be heard and needed to be withdrawn.

The real estate firms argued that a homebuyer had no choice and could only seek relief from Rera or from a consumer commission under the Consumer Protection Act, 1986. They maintained that since Rera itself gives an option to an allotte to withdraw pending proceedings under CPA, the same needed to be followed in cases filed elsewhere after Rera came into force.
However, HC rejected the argument and upheld a verdict of NCDRC, which said that the remedies provided under CPA and Rera are concurrent and the jurisdiction of the forums/commissions under CPA was not ousted by Rera.

Justice Jalan also cited a recent Supreme Court ruling in this regard to stress that there was no scope for any confusion, reiterating that parallel cases against the builder could proceed both under Rera and NCDRC for the benefit of the homebuyer. It said the relationship between proceedings under CPA and Rera had also been considered by the apex court.
However, the real estate firms claimed the SC ruling on them was not binding since litigation before the SC was on question of options available to a homebuyer under Rera once a builder’s company became insolvent under the new Insolvency Code. But HC highlighted that “issues arising out of CPA proceedings were also brought to the attention of the apex court.”

 

DISCLAIMER: This website and the Information contained is in the process of being updated and the contents are under review/revision in terms of the Real Estate Regulation Act, 2016 and Rules there under (RERA), and will be reviewed from time to time. Till the time that the contents are fully updated, the same shall neither be construed to be any kind of advertisement, solicitation, marketing, Booking, offer for sale, invitation to offer within the purview of RERA and shall have no binding effect on the Company and nor constitute any offer and/or acceptance and/or contract and/or agreement and/or transaction and/or any intention thereof and/or a disclosure under any statute of any nature whatsoever. Please call to check the updated pricing, status etc. The photographs contained herein may be actual/stock/standard photography or rendered images used for the purpose and have been taken at a location other than the project site and are used to indicate a conceptual lifestyle. Actual product may vary/differ from what is indicated herein. The location info shown are indicative and selective representation of certain elements present/that may be present in and around the city/project site. No representations are made regarding existence/continuity of existence of any landmarks/locations shown. The landmarks/locations may be subject to change from time to time and such changes are completely outside our control. No representation or warranty is made or intended as to the accuracy or completeness of information under this website or as to its suitability or adequacy for any purpose. Before making a decision to purchase, you are requested to independently, either directly or through your legal/financial consultants, thoroughly verify all details/documents pertaining to the respective project as available on the respective RERA sites.The Company is not liable for any consequence of any action taken by the viewer relying only on such material/ information that is presently displayed on this website.