News: Soil caves in at 2 spots, NHAI halts GMDA’s pipeline work along Dwarka Expressway-31-10-2025

https://timesofindia.indiatimes.com/city/gurgaon/soil-caves-in-at-2-spots-nhai-halts-gmdas-pipeline-work-along-dwarka-expressway-in-gurgaon/articleshow/124969470.cms

Gurgaon: A tussle has broken out between National Highways Authority of India (NHAI) and GMDA over a water pipeline being laid along Dwarka Expressway.

The highways authority halted the pipeline work a few days ago, citing safety issues and the absence of mandatory approval.

Soil subsidence was detected at two locations during excavation, prompting NHAI to suspend the work immediately. The 2,000mm diameter pipeline is being laid by GMDA to commission the Sector 72 boosting station, which would further supply water to sectors 58 to 80.

An NHAI official said, "They did not seek formal approval. During excavation, soil subsidence was noticed at two points. If it continued, it could have affected the stability of the expressway."

A senior GMDA official said the pipeline is critical to ensure adequate water supply to the newly developed sectors along SPR and Golf Course Extension Road.

"The work was supposed to be carried out by the NHAI during the construction of Dwarka Expressway. When they refused to undertake the work, it was decided at the higher level of govt that GMDA would complete the remaining portion. We have written to NHAI about this and we initiated the work to avoid delay in completing the water distribution network. After they stopped the work, we submitted a fresh request for approval and hope NHAI clears it soon," the official said. The Rs 8-crore project was awarded in April this year to plug a 350 metre gap in the water supply network near Sector 36A.

During the construction of the expressway, NHAI relocated an earlier water line passing under the Central Peripheral Road (CPR).

However, a 350 metre stretch near Sector 36A remained incomplete due to a land hurdle.

DISCLAIMER: This website and the Information contained is in the process of being updated and the contents are under review/revision in terms of the Real Estate Regulation Act, 2016 and Rules there under (RERA), and will be reviewed from time to time. Till the time that the contents are fully updated, the same shall neither be construed to be any kind of advertisement, solicitation, marketing, Booking, offer for sale, invitation to offer within the purview of RERA and shall have no binding effect on the Company and nor constitute any offer and/or acceptance and/or contract and/or agreement and/or transaction and/or any intention thereof and/or a disclosure under any statute of any nature whatsoever. Please call to check the updated pricing, status etc. The photographs contained herein may be actual/stock/standard photography or rendered images used for the purpose and have been taken at a location other than the project site and are used to indicate a conceptual lifestyle. Actual product may vary/differ from what is indicated herein. The location info shown are indicative and selective representation of certain elements present/that may be present in and around the city/project site. No representations are made regarding existence/continuity of existence of any landmarks/locations shown. The landmarks/locations may be subject to change from time to time and such changes are completely outside our control. No representation or warranty is made or intended as to the accuracy or completeness of information under this website or as to its suitability or adequacy for any purpose. Before making a decision to purchase, you are requested to independently, either directly or through your legal/financial consultants, thoroughly verify all details/documents pertaining to the respective project as available on the respective RERA sites.The Company is not liable for any consequence of any action taken by the viewer relying only on such material/ information that is presently displayed on this website.