News: Work on Sohna elevated road to remain suspended till safety measures are adopted: NHAI-01-09-2020

https://www.hindustantimes.com/gurugram/work-on-sohna-elevated-road-to-remain-suspended-till-safety-measures-are-adopted-nhai/story-EJVAhvlaAkLhA6Ac9RAKbM.html

The National Highways Authority of India (NHAI) on Tuesday said that work on Sohna elevated road project will remain suspended till adequate safety measures are taken on the entire project site. The authority has asked the contractor to ensure seamless barricading, covering the construction area, up to one-third of the height of the structure. It has also recommended the deployment of more security guards and traffic marshals. NHAI officials said that despite directions being issued last week, adequate measures have not been taken.

The work on Sohna elevated road project was temporarily suspended by the authority last Tuesday, following the collapse of a span between pier 10 and pier 11 on August 22. The authority has also formed a high-level technical committee, which is probing the incident.

Ashok Sharma, NHAI project director, on Tuesday said that work will continue to remain suspended till seamless barricading is put up at the entire project site and other safety measures are taken. Further, the contractor, Oriental Engineering, will continue to face a penalty of ₹50,000 per day. “The seamless barricading has not happened and the height of barricading in areas where construction work is being carried out has not been raised to one-third of the structure’s height,” said Sharma.

He further said that number of traffic marshals deployed at the site need to be increased to ensure safe movement of vehicles along the road. “The measures taken by the contractor are not satisfactory. Therefore, till an independent engineer doesn’t submit his report and verifies that requisite measures have been taken, the work will not be allowed to restart,” he said.

Members of the technical team that visited the site last Thursday also said that the contractor will not get any additional time on account of the delay caused by the accident.

The 21.66 km-long Sohna road project has two parts — an underpass and an elevated road from Subash Chowk to a point beyond Badshahpur. The second part comprises the expansion of12.72-km road from Badshahpur to Sohna and will involve the construction of flyovers and underpasses at major crossings to ensure smooth movement of vehicles on the entire stretch.

The deadline for both these projects is July, 2021. A senior official of Oriental Engineering said that they have taken all measures for barricading and improving safety and security of commuters and workers at the site.”Additional measures as per NHAI directions have been taken and more are in the offing. We hope that in next couple of days we will get permission to resume work,” he said on the condition of anonymity.

DISCLAIMER: This website and the Information contained is in the process of being updated and the contents are under review/revision in terms of the Real Estate Regulation Act, 2016 and Rules there under (RERA), and will be reviewed from time to time. Till the time that the contents are fully updated, the same shall neither be construed to be any kind of advertisement, solicitation, marketing, Booking, offer for sale, invitation to offer within the purview of RERA and shall have no binding effect on the Company and nor constitute any offer and/or acceptance and/or contract and/or agreement and/or transaction and/or any intention thereof and/or a disclosure under any statute of any nature whatsoever. Please call to check the updated pricing, status etc. The photographs contained herein may be actual/stock/standard photography or rendered images used for the purpose and have been taken at a location other than the project site and are used to indicate a conceptual lifestyle. Actual product may vary/differ from what is indicated herein. The location info shown are indicative and selective representation of certain elements present/that may be present in and around the city/project site. No representations are made regarding existence/continuity of existence of any landmarks/locations shown. The landmarks/locations may be subject to change from time to time and such changes are completely outside our control. No representation or warranty is made or intended as to the accuracy or completeness of information under this website or as to its suitability or adequacy for any purpose. Before making a decision to purchase, you are requested to independently, either directly or through your legal/financial consultants, thoroughly verify all details/documents pertaining to the respective project as available on the respective RERA sites.The Company is not liable for any consequence of any action taken by the viewer relying only on such material/ information that is presently displayed on this website.