News: NHAI to remove three toll gates at Sirhaul, expedite underpass work-09-01-2021

https://www.hindustantimes.com/cities/gurugram-news/nhai-to-remove-three-toll-gates-at-sirhaul-expedite-underpass-work-101610216484162.html

The National Highways Authority of India(NHAI) has got the nod for shifting three toll collection gates on the Delhi-Gurgaon Expressway, which have become a hindrance to the completion of the Sirhaul underpass project

The National Highways Authority of India(NHAI) has got the nod for shifting three toll collection gates on the Delhi-Gurgaon Expressway, which have become a hindrance to the completion of the Sirhaul underpass project. After a delay of several months, the NHAI got the approval from the South Delhi Municipal Corporation (SDMC) to shift the three toll plaza gates, which till now were being operated by the Delhi civic body.

The flyover at Shankar Chowk, which is a part of this project, has already been completed.NHAI officials said that once these gates are removed, they would be able to complete the underpass as only 20 to 25 percent of the work remains to be completed.

NHAI officials said that they would get an approval from the headquarters in this matter within a couple of days and the work to remove these gates would be completed in the next 15 days. “We have received a work estimate of â‚¹46 lakh from the SDMC to complete this work. The delay in removal of gates was hampering the completion of the underpass. The flyover at Shankar Chowk, which is also part of this project, has already been completed,” said Vikas Mittal, senior manager, NHAI, Gurugram.

The underpass at Sirhaul toll plaza will help commuters travelling from Gurugram and Udyog Vihar towards Ambience Mall as they would not have to enter Delhi to take a U-turn at Rajokri that amounts to a detour of around 4 kilometres. The demand for an underpass at this location has been repeatedly made by city residents.

NHAI said that functioning of three lanes of the toll plaza would be affected during the construction of the box type structure of the underpass. As such, it needed to shift these toll gates. They also said that almost 80 per work on the project is complete and, once the toll gates are shifted, they would be able to complete the project soon.

The work on building the underpass and flyover commenced in March 2019. While the flyover has been made operational by NHAI, the underpass is still stuck.

DISCLAIMER: This website and the Information contained is in the process of being updated and the contents are under review/revision in terms of the Real Estate Regulation Act, 2016 and Rules there under (RERA), and will be reviewed from time to time. Till the time that the contents are fully updated, the same shall neither be construed to be any kind of advertisement, solicitation, marketing, Booking, offer for sale, invitation to offer within the purview of RERA and shall have no binding effect on the Company and nor constitute any offer and/or acceptance and/or contract and/or agreement and/or transaction and/or any intention thereof and/or a disclosure under any statute of any nature whatsoever. Please call to check the updated pricing, status etc. The photographs contained herein may be actual/stock/standard photography or rendered images used for the purpose and have been taken at a location other than the project site and are used to indicate a conceptual lifestyle. Actual product may vary/differ from what is indicated herein. The location info shown are indicative and selective representation of certain elements present/that may be present in and around the city/project site. No representations are made regarding existence/continuity of existence of any landmarks/locations shown. The landmarks/locations may be subject to change from time to time and such changes are completely outside our control. No representation or warranty is made or intended as to the accuracy or completeness of information under this website or as to its suitability or adequacy for any purpose. Before making a decision to purchase, you are requested to independently, either directly or through your legal/financial consultants, thoroughly verify all details/documents pertaining to the respective project as available on the respective RERA sites.The Company is not liable for any consequence of any action taken by the viewer relying only on such material/ information that is presently displayed on this website.